Te Huka Steamfield, Taupo
The Te Huka Unit 3 will be an additional unit at the exisiting Te Huka geothermal power station located In Taupo, New Zealand.
The plant is incorporating a novel design which will enable the carbon emissions from the project to be reinjected into the reservoir in the future. Continuing on with their current works in the vicinity for Contact Energy, Warner construction were at the ready to start this assignment immediately after finishing the Tauhara Steamfield.
Te Huka Steamfield
Date: 2023 - Due completion April 2024
Client: Contact Energy
Length: 5kms (approx)
Size: 500NB & 750NB
Fast facts:
1 x Reinjection line
1 x Production line
Venting and separation & SGW Plant