Te-Mihi SF2

Contact Energy

August 2011

Wairakei, Waikato

Length: 3.5km

Size: 100NB and 200NB

All of the welders were ASME IX qualified and working to the ASME B31.1 code. The Steam Lines were 100% radiographed.

The project was a very difficult time driven project run during the winter months. Warner Construction Ltd achieved all specified targets.

This project was the installation of twin pipelines from the Sidewinder Production Station to tie-in with a Vector line on Upper Durham Road.

Our scope included Welding, Wrapping, Lower and Lay, Civil and Hydro-testing. We also performed the Hot Tap into the Vector line and the construction of the tie-in compound.